Downey High School - Project Update - Wednesday January 21, 2009
Wednesday, January 21, 2009

Acme - We are finishing up in the 200''s north and moving into the gov. north to start wall framing in the restrooms. We will be moving into the 80''s wing to start the clerestory infill. We will also start the 80''s demo in the weeks to come . The field house is waiting on the toilet partitions, they are due here at the end of next week.

Patrias - Is in the gov. north installing the existing can lights. And in the 80''s doing lay out for demo

Pinasco - Is in the gov. north working on the plumbing rough-in in the restrooms and working on demo lay out in the 80''s.

DC Veint - Is painting the gov. wing and then they will move to the 200''s north to start prep work for paint.

Western - Is in the 200''s north working on the tack board. Rigid vinyl and the suspended ceiling.

APC - Has demoed the 200''s north roof and has started work on the 80''s roof.

Tru-Tech has started work on the 200''s north roof and they will follow the abatement crew into the 80''s wing.

In the weeks to come we will be moving into the 80''s wing to start lay out for demo. We will also be working on finishing up with the 200''s north. gov.north, weight room, and the field house.




Downey High School - Project Update - Wednesday January 14, 2009
Wednesday, January 14, 2009

Acme - Is currently in the gov. north woeking on restroom floors doing prep for concrete and in the weight room working on door hardware, wall in-fill. We are going through installing doors that were back ordered.

Patrias - Is in the gov. north, 200''s north, and weight room working on electrical rough-in and moving into the 80''s wing to do rough-in.

Pinasco - Is in the gov. north working on plumbing rough0in for the new restrooms and moving into the 80''s to start lay out for the floor demo.

DC Vient - Is patching wallpaper and painting interior of gov. north and also painting esterior of gov. bldg.

Modern Air - Is installing the new bard units at the 200''s north and weight room.

APC - Test were taken on the 80''s and passed. Now they are working on soft demo and in the next few days they will start to demo the 200''s roof and also the 80''s roof.

Kent Lathing - Is installing sheetrock in the 200''s north.

Western building - Is starting to install the rack board in teh 200''s north the eigid vinyl and suspended ceiling will follow.




Downey High School - Project Update - Wednesday January 7, 2009
Wednesday, January 07, 2009

Acme - is currently in the gov. north working on demo. In the 200''s north working on wall framing and graming for bard units. In the Weight room working on door hardware, wall infill,and setup on the new ramp and in the field house framing and in0fill.

Patrias - Is in the gov. north, 200''s north, and weight room working on electrical rough-in

Pinasco - Is in the gov. north working on plumbing rough9in for the new restrooms.

DC Vient - Is patching wallpaper and painting interior of gov. north and also painting esterior of gov. bldg. on clear days.

Modern Air - Is installing the new bard units at the 200''s north and weight room.

APC - Is in the 80''s working on the abatement and will be ready for testing on Monday 1-12-09 and then start on the soft demo.

Kent Lathing - Is installing sheetrock in the 200''s north.

Golden State - Is installing lath and plaster to the exterior of clerestory at the 200''s north and the weight room.

Concrete Installations was here grinding, staining, and polishing the main hallway floors.

HW Thompson - Is in the main hallway installing the new base.




Downey High School - Project Update - wednesday December 17, 2008
Wednesday, December 17, 2008

Acme is working in the gov. bldg. installing interior doors and hardware, also working on the weight room framing in the clerestory and for bard units we are workign on the ramp in the weight room.

Patrias - is finished with the gov. bldg. south and have started electrical rough-in for the bard units.

DC VIent - is painting exterior of gov. and interior touch up of gov. south

Pinasco - is workign in the field house working on plumbing rough-in

APC - will finish the gov. north by 12-19-08 and run tests on 12-22-08 then they will move to the 200''s north to start containment for abatement and also do removal of base in the wieght room.

In the weeks to come we will be moving into the 200''s north/ gov. north/ 80''s east and also over winter break we will start work on the hallways with the polishing.




Downey High School - Project Update - Wednesday December 10, 2008
Wednesday, December 10, 2008

Acme - We are in the gov. bldg. installing doors and hardware and we also have a crew in the field house installing new door jambs, doors, and hardware and doing demo work for plumber.

Patrias - is in the gov. bldg. south working on the new electrical panels and finishing the wire mold. Also in gov. north working on demo.

Pinasco - is in the field house working on demo

DC VIent - is in the gov. south interior paint and touch-up and working on exterior prep and paint

Western - Installed all the ceiling tile in gov. south

HW Thompson- Is installing new carpet in gov. South

APC - is in gov. north removing carpet and stting up containment for abatement.

Friday we are moving into the weight room to start working on the clerestory infill. framing for the bard units, all wall infills, doors and hardware and installing the new ramp and we also have gov. north and 80''s east coming up.




Downey High School - Project Update - Wednesday December 3, 2008
Wednesday, December 03, 2008

Acme - We are finished with 50''s wing and moving into the gov. bldg. installing esterior doors and hardware. We are also in the boys restroom of the 80''s wing rough framing and blocking. We are moving through out the site installing any doors that we have had back ordered. And we have also started working on the field house.

Patrias - Patrias has moved into the gov. bldg. doing electrical rough-in and installing wire mold. and in the 80''s restroom and field house also doing rough-in.

DC Vient - Vient is in the gov. bldg. patching walls with wall paper and painting. Painting exterior of any bldg. that we can paint at this time.

Modern Air - Modern is in the 80''s restroom installing exhaust fan and in the auditorium basement doing mechanical demo.

Pinasco - Pinasco is in the 80''s restroom doing rough plumbing and in the field house working on demo

In the weeks to come we will be working on the 80''s restroom. the gov. bldg painting, electrical, ceiling tile, carpet, doors and hardware. To meet our dead line for Christmas break we are also in the field house working on plumbing, electrical, and painting new doors and hardware. On the 12th we will also be moving into the weight room to start work.




Downey High School - Project Update - Wednesday November 19, 2008
Wednesday, November 19, 2008

Acme - We are installing weather stripping to all or our new doors. Finishing hardware, kick plates, thresholds. We are working on the 80''s boys bathroom framing, blocking and working on the h/c ramp in the front of the auditorium.

Patrias - Installing wire mold in the 50''s and ready to statr electrical rough-in at the gov. building.

{inasco - Plumbing rough-in in the 80''s bathroom boys and ready to start work on gov. bathroom.

DC Vient - Finish painting interior of 50''s and working on exterior.

Western - Tack board and rigid vinyl in 50''s.

APC - Finish abatement in gov. north and ready to start gov. south.

JR Stephens - Install casework in 50''s.

Decorator Draperies - intalling window binds in 70''s and 80''s, administration, and library.




Downey High School = Project Update - Wednesday November 5, 2008
Wednesday, November 05, 2008

Acme - Installing doors, door jambs, and hardware in 50''s and gym. Installing hard rails in 70''s wing. Installing new benches in front of school main entrance. We are starting to work on the ramp in front of the auditorium.

Patrias - Electrical rough-in in 50''s wing and connecting power to new boiler

Pinasco - demo of toilets, urinals and sinks in boys restrooms of 80''s wing

Kent Lathing - Sheetrock, tape and wall prep in 50''s wing

Golden State Plaster - Applying plaster to clerestory in 50''s

We are finishing our work on the 50''s wing rough-in and now starting back on out finish electrical, tack board, ridged vinyl, paint and carpet, and the teachers restrooms, sheetrock, tile, epoxy floors, toilets, sinks, urinals, doors and paint. We are preparing to start working on the gov. bldg. after APC in sinished with abatement.




Downey High School - Project Update - Wednesday October 29, 2008
Wednesday, October 29, 2008

Acme - Demo and install doors and frames. Demo walls and rough frame for restrooms. Finish work on clerestory and prep for lath and plaster. Also we are starting work on the swimming pool.

Patrias - Fough-in on the 50''s installing conduit and installing electrical boxes and start work on pool.

Pinasco - Plumbing rough-in in 50''s restrooms. Install toilets and sinks in 30''s. Getting ready to work on pool project.

Modern Air - Installing duct work in the 50''s. Finishing work on bard units and do startup on the units in 30''s.

Shelco - Install toilet partitions in 30''s restrooms

Golden State Plaster - Lath and plaster in the 50''s clerestory

Kent Lathing - Installing sheetrok in 30''s wing

D.C. Vient - Finish paint in the 30''s and move to 50''s

Fagundes and Sons - Start work on pool demo




Downey High School - Project Update - Wednesday October 22, 2008
Wednesday, October 22, 2008

Acme - We are finishing our work on the 30''s and we are moving to the 50''s to start our work on clerestory in-fill. Demo of walls for electrical. Demo of restroom walls. Wall In-fill.

Patrias - Working on the last of the wire mold in the 30''s and moving to 50''s wing to start demo and rough-in.

Pinasco - Moving to 30''s to start demo in the restrooms removing existing accessories and start rough-in.

Modern Air - Working on down spouts and gutters. Flashing and mechanical rough-in in 30''s and 50''s.

DC Vient - Finish paint to interior of 30''s and prep work to exterior of 30''s for paint.

H.W. Thompson - Installing carpet to classrooms of 30''s.

L.R.F. Flooring - Appling epoxy floot system to the restroom in 30''s.

Tru-Tech - Finish patching the roof at the clerestroy for the new ringlet.

A.P.C. - Working on the soft abatement of 30''s wing.





Downey High School - Project Update _ Wednesday October 15, 2008
Saturday, October 18, 2008

Acme - installing new doors. Door jambs and hardware per phase one and two. Installing finish trim to 30''s wing around doors and across ceiling. Finishing moe strip. Repair the eves on the 50''s roof and build curbs.

Patrias - Install wire mold in the 30''s wing. Install conduit and pull wirre for the bard units in the 30''s. Install plugs and switches.

Pinasco - Run gas lines to bard units. Install new boiler in boiler room and install plumbing.

Modern Air - Installing bard units in 30''s wing. Installing new gutters on 50''s roof and installing down spouts.

DC Vient - Paint walls, ceilings, and casework in 30''s and prep exterior for paint.

Western Building Materials - Installing tack board. Rigid vinyl in the 30''s wing.

Golden State Plastering - Finish infill to the clearstory in 30''s wing.

Shelco - Install toilet partitions in 40''s wing - room 44.

Tru-tech - Install new roof on 50''s high roof

AAI - Install tile in the girls restroom of the 30''s wing.

APC - Continue with the abatement in the 50''s wing,

We will continue to work on the 30''s wing finishing up with the electrical, mechanical, tack board, rigid vinyl, paint, carpet, tile, doors and hardware, bathrooma nd accessories to finish by our 10-31-08 dead line. We will also be starting on the 50''s wing. APC will have abatement and containment finished by 10-17-08 and by the following Monday we will be in the 50''s working.




Downey High School - Project Update - Wednesday October 8, 2008
Wednesday, October 08, 2008

Acme - Wall in-fill, clearstory, installing door jambs, doors, and hardware in 30''s wing. Moe strip in courtyard. Backing in restroom of 30''s for toilet partitions. Repair dry rot on 50''s wing roof.

Pinasco - Installing new boiler in existing boiler room. Installing toilets in restrooms in lobby of boys gym. Run gas lines to the new bard units in 30''s wing.

Patrias - Wire mold in the administration building. Electrical rough-in and starting wire mold in the 30''s wing.

Modern Air - Gutters, Flashing and downspouts in 30''s and 50''s wing. Installing bard units in 30''s wing.

DC Vient - APaint lobby of boys gym. Paint the rest of phase 1 and start phase 2.

Western Building Materials - Installing ridged vinyl and tack board in 30''s and boys gym lobby.

APC - Start abatement in 50''s wing and start abatement on the roof of 50''s wing.

Signs your way - Installing signage through phase 1.

Golden State Plaster - Finish exterior of clearstory with plaster finish.

Kent Lathing - Sheetrook / tape and prep for paint finish in 30''s wing.




Downery High School - Project Update - Wednesday October 1, 2008
Wednesday, October 01, 2008

Acme - Continue work on 30''s wing doing wall in-fill. Clearstory in-fill. Rough framing for bard units. Repairing dry-rot at the eaves. Door trim in administration around new door jambs and light cleanup.

Patrias - Electrical rough-in in the 30''s wing. Installing conduit for new bard units. Installing wire mold in the administration building.

Pinasco - Installing gas lines to brad units. Installing toilets, sinks, and urinals and rough-in in the 30''s wing.

Modern Air - Installing gutters to the 30''s wing. Connecting a/c units on the administration and installing registers.

Western Building Materials - Installing tack board, rigid vinyl, and suspended ceilings in the administration building.

H.W. Thompson - Installing carpet in the administration offices.

Concrete Installations - Staining the concrete floors in boys gym lobby.

Kent Lathing - Installing sheetrock to the wll in-fills. Clearstory''s and restrooms in the 30''s wing.

Golden State Plaster - Prep work fo r30''s wong. Installing lath ans stucco to the exterior of clearstory in the 30''s wing.




Downey High School - Project Update - Wednesday September 24, 2008
Wednesday, September 24, 2008

Acme - Start demo in 30''s wing for electrical rough-in and start wall infills and clearstroy infills. Finish work in administration building. Installing door frames and hardware to boys lobby main entrance.

Patrias - Installing lights in T-bar ceiling at the administration building. Start electrical rough-in in 30''s wing.

DC Vient - Painting through out phase I

Pinasco - Installing bathroom accessories in lobby restrooms and restroom #44. Finish work on A/C units.

Western Building Materials - Installing T-bar ceiling and ceiling tile in administration building. Start tack board in room 1a, 1b and start rigid vinyl.

LRF - Epoxy floors in rostrooms.

Modern Air - Installing registers in T-bar ceiling. Connecting A/C units at the administration building.

HW Thompson - Install carpet tiles in administration building.




Downey High School - Project Update - Wednesday September 17, 2008
Wednesday, September 17, 2008

Acme - installing doors, door jambs and hardware in the administration building. Finish wall fill-in, mechanical curbs and trim. In the boys gym lobby we are inatalling the new doors to the front entrance and also finishing the rest of the doors and jambs throughout the gym. Finishing moe strips.

Pinasco - Installing toilets, urinals, and sinks restrooms #44 and in lobby of boys gym. Finish connecting gas lines to MUA's at the gym.

Patrias - Finish wiring and installing lights, plugs, and switches in the Administration Building.

Modern Air - Installing registers in the suspended ceiling in the Administration building. Connecting MUA's at the gym.

A.A.I. - Installing tile to walls at restrooms #44 and boys lobby restrooms.

A.P.C. - Abatement in 30's wing. Test passed and taking down containment so they can start soft demo.

Kent Lathing - Installing sheetrock for new rigid vinyl in room 1-A.

Western - Installing suspended ceiling to offices in the Administration Building.

L.R.F. - Applying epoxy floor finish to restrooms #44 and gym lobby.

DC Vient - Painting per phase I.

Concrete Solutions - Stain boys gym lobby floor.

Shelco - Installing toilet partitions in restrooms #44 and gym lobby.




Downey High School - Project Update - Wednesday September 10, 2008
Wednesday, September 10, 2008

Acme - Moe strip at 80's and 50's wing, installing door jambs, doors and hardware at library, book room, work experience, and computer rooms. Frame and prep walls and windows for new ceiling in administration building. Frame curbs for new mechanical a/c units in administration building.

Modern Air - Installing new duct work and insulating throughout administration building. Thursday and Friday morning our new MUA units will be arriving for the gym and we will be installing them on Tuesady morning to take advantage of the minimum day.

Patrias - Working in the administration building installing new plugs, switched, wire mold. Pulling wire inthe tunnels and connecting a/c units.

Pinasco - Connecting gas lines to all the bard units that were installed. Installing new hot water lines in the training room in the boys locker room. Relocating the new boiler from th girls locker room to the existing boiler room.

DC Vient - Paint exterior of administration building. Touch up paint in the library and paint restromm #44 and lobby restrooms.

Western Builidng Materials - Start to install new suspended ceiling in administration building.

A.A.I. - Installing tile in restroom #44 and move to lobby restroom.

Signs Your Way - Installing signage throughout phase 1 on 9-15-08.




Downey High School - Project Update - Wednesday September 3, 2008
Wednesday, September 03, 2008

Acme - Installing doors, jambs, and hardware in the hallways and library. Work in administration building, framing in windows and blocking for suspended ceilings. Installing mow strips throughout site.

Patrias - Pull wire in library. Start rough-in at the administrtion building. Work on fire alarm, phone lines, data

Modern Air - Installing bard units to boys gym, duct work in the administration building.

Kent Lathing - Installing drywall to bathrooms.

Pinasco - Plumbing rough-in. Installing gas lines to bard units in gym.

A.P.C. - Start abatement in 30''s wing

Golden State Plaster - Prep walls for new rigid vinyl in boys lobby

DC Vient - Paint exterior of gym, library, doors, frames and administration building.




Downey High School - Project Update - Wednesday August 27, 2008
Wednesday, August 27, 2008

Acme - Installing mow strip throughout site. installing doors, jambs, and hardware in boys and girls gym and library. build curbs for mechanical units and clerestroy infill in administration building.

Modern Air - Mechanical rough in duct work. set A/C units. bard units in 80's wing, administration building, library, and gym.

Patrias Electric - Wire mold. Pull wire in library. Connect bard units in gym.

Pinasco - plumbing rough in at the boys gym lobby. Connect shower heads and valves in girls lobby.

DC Vient - Paint boys and girls gym inside and out, library, and hallways.

We will be ready to turn over the boys and girls gym on 9-2-08 to allow students to dress out and coaches to move in. However we eill still have some loose ends to deal with such as installing a/c units. brad units, thermostats. We will try to take care of them before or after school or when kids are not present.




Downey High School - Project Update - Wednesday August 20, 2008
Wednesday, August 20, 2008

Acme - Finis work on 70''s and 80''s tack board, rigid, carpet, base, tile, trim, doors, hardware, electrical. Final cleanup in gym, door frames tirm, framing in lobby, library, framing boys bathroom prep for tack board and rigid, Administration, rough framing, prep floors in hallway.

Patrias - Final trim work in 70''s and 80''s wing. Installing wire mold for fire alarm in the administration. Electrical rough-in.

Pinasco - Installing gas line in boys and girls gym, library, 70''s and 80''s wing, plumbing rough-in in room 44 library wing.

DC Veint - Paint interior buildings. Interior and exterior gym, library, 70''s and 80''s wing.

Kent Lathing - Install sheetrock for rigid board in library. Infill walls.

Western Building Material - Installing ceiling grid. tack board, and rigid.

Modern Air - Mechanical rough-in in administration duilding. Installing registers. bard units in 70''s. Curbs on administarion.

Golden State Plastering - Tile in shouwer of girls locker room

Shelco Industries - Install toilet partitions in boys and girls locker rooms.

I.C. Electronics - Install fire alram, clocks and speakers.

Fagundes - Paving front of boys gym. Old playground area and some patch work




Downey High School - Project Update - Wednesday August 13, 2008
Wednesday, August 13, 2008

Acme - Pour concrete in gym area, setup ramp and stairs in front of boys gym entrance. Frame work for brad units in gym. Fur wall out in room 1a. Start work in administration rooms.

Patrias - Install wire mold in 70s and 80s wind, library, and gym. Installing lights and electrical rough-in in library. Installing thermostats and alrm system.

Modern Air - Mechanical lay out for a/c curbs and duct work in the administration building. Gutters and flashing .

Pinasco - Plumbing rough-in in boys lobby and boys bathroom # 44. Installing gas line on gym roof for mechanical.

D.C. Vient - Paint gym area, library, 70''s and 80''s wings, administration hallway, and library hallway.

Tru-Tech - Install roof system on administration roof, 1a, 1b, and patch work at column locations.

Western - Installing tack board, suspended ceiling, glue up ceiling and rigid vinyl wainscot.

HW Thompson - Installing carpet in 70''s and 80''s rooms, boys locker team room, and daycare.




Downey High School - Project Update - Wednesday August 06, 2008
Wednesday, August 06, 2008

Acme - library work demo for electrician, clerestroy in fill, framing for mechanical, framing of bard units in gym, dry pack holes in walls and prep for paint, finish framing girls showers, set up and pour concrete sidewalks, moe strips, bathroom floor in boys gym and dry pack in girls gym. grade dirt for new grass in 100's wing at nursery.

Patrias - finish work in 70's and 80's wing. working in library and gym pulling wire and hooking up panels.

Pinasco - plumbing rough in, in girls showers, boys lobby, boys restroom in 40's wing and installing gas line for bard units in gym.

Modern Air - mechanical rough in, in boys gym, 70's and 80's wing, and library.

Western Building Material - Installing tack board, wainscot, suspended ceiling in 80's wing.

Tru-Tech - installing roof system to gym roof, patch work in all wings to gutters and flashing

DC Vient - painting boys and girls gym, library, administration building, and 70's and 80's wing.

IC Electronics - reconnecting fire alram for phase 1

AAI - installing tile in bathroom of boys and girls locker rooms, and girls shower room.




Downey High School - Project Update - Wednesday July 30, 2008
Wednesday, July 30, 2008

Acme - Columns, sidwalks, ramps, mowstrips. Rough framing in boys and girls gym for plumbing. Library - frame clearstory. Install 1x material to ceiling for sheetrock backing.

Pinasco - Rough-in plumbing in boys gym lobby restrooms. Installing new gas line on gym roof. Demo and rough plumbing in library restroom.

Modern Air - Installing mechanical curb onlibrary roof. Installing gutters and flashing for phase 1: 100''s, 80''s, 70''s, 50''s, 30''s, 200''s, and gym.

Patrias - Installing flush duct in library floor. Working in 70''s and 80''s east. Pull wire in gym.

Western Building Material - Installing tack board, suspended ceiling, and wainscoat in 70''s and 80''s west.

D.C> Vient - Painting 70''s 80''s west, Gym, and flag pole.

Fagundes - Site work grading, fire hydrant, and clean out existing rockwells.

Tru-Tech - Installing roof system on gym roof and canopies 70''s, 80''s, 100''s, 30''s, 200''s, and 50''s.

We also have tile, carpet, cabinets, counter tops, ect. coming soon as job continues.




Downey High School - Project Update - Wednesday July 23, 2008
Wednesday, July 23, 2008

Acme - Backing for Fire extinguishers cabinets and marker boards. Bard unit framing. Installing wood nailer in the 70's and 80's wing. Blocking, backing, and framing skylite infill. Platforms and crickets at gym. Still working on columns for canopy. Site concrete: sidewalks, ramps, mowstrips, and columns.

Patrias - pulling wire in the 70's and 80's wing. Start rough-in at the library. Saw cut floors. Rough in at the boys and girls locker room.

Pinasco - Rough in at the boys and girls locker room: showers, sinks and fountains.

Modern Air - Installing new duct work in the boys and girls locker room. Gutters.

Kent Lathing - Continue sheetwowk on the 70's and 80's wing.

Fagundes - Continue sitework demo.

A.P.C. - Remove gutters. Abate library hallway tile. Abate Administration building and rooms 1A and 1B. Abate roof at rooms 1A and 1B.




Downey High School - Project Update - Wednesday July 16, 2008
Wednesday, July 16, 2008

Acme - Continue work at columns and grade beams at canopy. Work at 70's and 80's west. Wall infill. Clearstory infill. Blocking for machanicals on roof in the 80's wing. Framing for bard units in 70's west wing. Gym blocking and platforms for mechanicals. Roof repair at eaves for dry rot and prep for gutters. Site concrete: sidewalks, ramps, and mowstrips around trees.

Patrias - Electrical rough in. Emergency lighting. Pull wire in tunnels.

Pinasco - Plumbing rough in at boys and girls locker rooms.

Fagundes - Site demo: sidewalks and ramps.

Kent Lathing - Installing sheetrock in the 70's and 80's wing.

Golden State Plaster - Stucco at exterior of clearstory in the 70's and 80's wings.

Modern Air - Installing duct in gym. Gutters. Layout mechanical curbs and fans ingym.

A.P.C. - Abatement on gym roof. Set up for abatement in the administration building. Abatement continues in the library.




Downey High School - Project Update - Wednesday July 12, 2008
Saturday, July 12, 2008

Acme - Framing on roof at the gym. Framing at the 70's and 80's west building. Setup and pour concrete for grade beams and columns at canopy.

Patrias - Fire alarm. Surface mount conduit in 70'2 and 80's west wing. rough in at boys and girls locker rooms.

Pinasco - Rough in bathrooms atboys and girls locker rooms and 40's eing after soft demo.

Modern Air - installing A/C duct in girls locker romm and continue throughout gym. Lay out in adminsitration building.

A.P.C = APC turned over the 70's and 80's wings to Acme on 7-8-08 and moved over to the library to start containment for abatement. Abatement continued int he boys and girls locker rooms. Gutter removal throughout phase 1.




Downey High School - Project Update - Wednesday July 02, 2008
Wednesday, July 02, 2008

Acme - Continue work on the canopy. Start work in the 80's wing, building walls. Infill at clearstory. Working at gym. Blocking for the mechanicals. Build platforms on roof for new units.

Pinasco - Continue installing new gas. layout in restrooms for demo.

Patrias - 70's and 80's rough in new conduit. Fire alarm.

Modern Air - Gym layout. Working in library and Administration building.

A.P.C. - Abatement in boys and girls locker rooms. Demo of gutters and roof. Clearstory windows.




Downey High School - Project Update - Wednesday June 25, 2008
Wednesday, June 25, 2008

Acme - continue to work on canopy sidewalk. Demo windows in the boys and girls locker room for new mechanicals. Build platforms on the boys and girls gym roof. At the 80's west wing - start new walls infill clearstory windows.

Pinasco - Continue to install new gas line at the 70's, 80's, library, admin building, and gym. Layout in bathrooms for demo and saw-cut.

Modern Air- Demo the boys and girls gutter and duct. Start exhaust and interior exposed duct work in the locker room. Layout for exhaust fan mechanical platform.

Patrias - Fire alarm in library. Dig trench norht of the 80's for the new electrical. finish backfill at the gym.

A.P.C. - Demo in the 80's building is 90% complete. Start containment in the 70's west for abatement. Demo high roof at the boys and girls fym. Start containtment for abatement in the boys and girls locker room.




Downey High School - Project Update - Wednesday June 18, 2008
Wednesday, June 18, 2008

Acme - Continue work on Caissons in all wings / Demo windows in boys and girls locker room / Framing for new mechanicals units in boys and girls locker room / Layout and frame work in the roof of boys and girls locker room.

A.P.C. - Abaitment in 70's and 80's West Wing / New crew to come on 6-23-08 to start demo on canopy of 70's and 80's West Wings / Third crew to show by end of month.

Patrias - Dig trench / Install conduit and backfill by the 50's wing / Install conduit in boys and girls locker room for the new fire alarm / Demo AC Electrical on Administration Building.

Modern Air - Boys and girls locker room layout for mechanical / Demo exposed duct at the Administration Building / Layout the AC for demo in Library.

Pinasco - Installing new gas line for Phase I.




Downey High School - Project Schedule Outline
Thursday, June 05, 2008

Phase I - June 5 to Oct. 2008

1. 70's / 80's West Wing
2. 40's Wing - Library
3. Gym - Boys
4. Gym - Girls
5. Admin & Admin Classroom - Site Work /
Seismic Col - All Wings

Phase II - Oct. to Jan 2009

1. 30's / 50's Wing Classrooms

Phase III - Jan. to March 2009

1. 60's / 70's / 80's Science Wing

Phase IV - April to Sept. 2009

1. Auditorium
2. Cafeteria
3. AG Wing
4. Shop Wings
5. Portables / Relocate
6. Site Work

Phase V - Sept to Jan. 2010

1. Government Building / Classroom
2. Drafting Classroom / Boiler Area