Downey High School Modernization

Modesto, Ca



Architect: Timothy Huff and Associates
Contract Amount: $14 m

Project Manager
» Ron Kettelman
Superintendent
» Joe Reynosa







Downey High School - Project Update - Wednesday January 21, 2009
January 21, 2009

Acme - We are finishing up in the 200''s north and moving into the gov. north to start wall framing in the restrooms. We will be moving into the 80''s wing to start the clerestory infill. We will also start the 80''s demo in the weeks to come . The field house is waiting on the toilet partitions, they are due here at the end of next week.

Patrias - Is in the gov. north installing the existing can lights. And in the 80''s doing lay out for demo

Pinasco - Is in the gov. north working on the plumbing rough-in in the restrooms and working on demo lay out in the 80''s.

DC Veint - Is painting the gov. wing and then they will move to the 200''s north to start prep work for paint.

Western - Is in the 200''s north working on the tack board. Rigid vinyl and the suspended ceiling.

APC - Has demoed the 200''s north roof and has started work on the 80''s roof.

Tru-Tech has started work on the 200''s north roof and they will follow the abatement crew into the 80''s wing.

In the weeks to come we will be moving into the 80''s wing to start lay out for demo. We will also be working on finishing up with the 200''s north. gov.north, weight room, and the field house.