Downey High School - Project Update - Wednesday January 7, 2009 January 07, 2009
Acme - is currently in the gov. north working on demo. In the 200''s north working on wall framing and graming for bard units. In the Weight room working on door hardware, wall infill,and setup on the new ramp and in the field house framing and in0fill.
Patrias - Is in the gov. north, 200''s north, and weight room working on electrical rough-in
Pinasco - Is in the gov. north working on plumbing rough9in for the new restrooms.
DC Vient - Is patching wallpaper and painting interior of gov. north and also painting esterior of gov. bldg. on clear days.
Modern Air - Is installing the new bard units at the 200''s north and weight room.
APC - Is in the 80''s working on the abatement and will be ready for testing on Monday 1-12-09 and then start on the soft demo.
Kent Lathing - Is installing sheetrock in the 200''s north.
Golden State - Is installing lath and plaster to the exterior of clerestory at the 200''s north and the weight room.
Concrete Installations was here grinding, staining, and polishing the main hallway floors.
HW Thompson - Is in the main hallway installing the new base.